      Hi.

      If I change some code within an orchestration (In an Expression shape for instance) do I have to redeploy the dll or is it enough just gacing it ? I want to avoid redeploying the orchestation’s dll (in PROD servers) as much as possible and I wonderd if I could only throw it to the GAC (stop the host, throw the dll to the GAC and start the host) while there are orchestration instances running (in an “Active” status). Again, I’m looking for a way to “update” the orchestration while there are running instances of it without redeploying it (just gacing it). Does anybody know if it is possible ?

      Thanks.

       

       

    • #18605

      Hi there

       Interestingly enough this has come up on a few projects I have worked on. And yes you can just regac it like thus …
      gacutil -if myAssembly.dll with the appropriate stop/start of the services.

      Of course you could just try it on your test system – after all that is what it is therefore right?